City of Bloomfield Hills - 2019 Road & Infrastructure Update

Water Main Work 


Kennebec Court

Water main and water service connections have been completed on Kennebec Court.  Residents will see the storm sewer work underway as well as road preparation for paving. 

Sebago Lane

The contractor is working on the water service connections to the new water main line.  

Merrimac 

Crews are completing water service connections on Merrimac.  

Falmouth

Water main and water service connections are the focus for crews on Falmouth.  After the connections are made, residents will see the road being prepped for paving work.  

Rudgate & Marblehead

The work on Rudgate & Marblehead will be water main connection work will begin the middle of next week.  

If you have questions, please contact the following individuals on the project team:

Onsite Field Representative Tom Cairo  (248) 535-3437
Project Engineer Melissa Coatta (248) 454-6567

Road Paving Work 


The paving work is anticipated to begin once the water main work is nearing completion.  To plan for the best routes to avoid truck travel over the new pavement, the road paving work at this time is planned to occur in the following sequence: 
  • Kennebec / Falmouth / Bennington
  • Sebago / Merrimac
  • Rudgate / Marblehead
New concrete curb and gutter will be installed on Kennebec, Sebago and Merrimac.  As the schedule is set for this work, we will continue to communicate via e-newsletter and with informational flyers delivered to the affected properties.  

If you have questions on the road paving project, please contact the following individuals on the project team:

DPW Foreman Jamie Spivy (810) 656-7531