City of Bloomfield Hills  - 2019 Road & Infrastructure Program

Sebago and Merrimac 
Water main has been installed on both of these streets and they are now in the testing phase.  

Falmouth 
Crews have started the water main installation on Falmouth.  The testing of the new water main on Falmouth is scheduled for next week.  

Rudgate
Residents on Rudgate will see construction activity on the water main after the installation work on Falmouth is complete.  

We understand it may appear that work is at a standstill on the streets that are in the testing phase. The testing of the system prior to the connections and service transfers is an important, but mostly behind the scenes, part of the project.  

Once the water main is installed and tested on all of these streets, the contractor will then start the water main connections and service transfers on Kennebec, Sebago, Merrimac, Falmouth and Rudgate.  As the work progresses, we will keep you informed on the specific timeline for this work.  

If you have questions, please contact the following individuals on the project team:

Onsite Field Representative Tom Cairo  (248) 535-3437
Project Engineer Melissa Coatta (248) 454-6567

Powered by CivicSend - A product of CivicPlus