City of Bloomfield Hills - 2019 Road & Infrastructure Program

Kennebec Court 

  • Water main is installed and is in the testing stage.

Sebago Lane

  • Crews continue to work on the water main installation.  

Merrimac Court 

  • Residents on Merrimac Court will see work begin on Monday, June 10th.  The road will be milled down on Monday and the water main installation is scheduled to begin the middle of the week, dependent on weather.
  • Temporary mailboxes will be installed, please check your mail daily to ensure there is no delay in service with the postal service.  
  • Residents will receive a letter mailed to your home with information specific to your property and any work that will be done in the road right of way near your home. Questions about right of way work should be directed to the Project Engineer Melissa Coatta at (248) 535-3336.  

Road & Infrastructure Program Contacts
 General Inquiries – City Hall                               (248) 644-1520
 Field Representative Tom Cairo                         (248) 535-3437
 Contractor Concerns Melissa Coatta                  (248) 535-3336





Powered by CivicSend - A product of CivicPlus